FY2026 GAA: ₱6.79T
PisoScan

Project 24AJ0005

DPWH infrastructure contract
Contract ID:
24AJ0005
Fingerprint:
dba55e41d2ef05…fc3e936962 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 6, 2024 (2 yrs 9 mo ago) · Target/actual end Mar 13, 2024
Description:
CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, BARANGAY BUENGLAT, SAN CARLOS CITY, PANGASINAN
Category:
Flood Control and Drainage
Implementing office:
Contractor:
JEUSMACK BUILDERS & CONSTRUCTION SUPPLY · DPWH contractor code 42334
Contract amount:
₱4,949,825.62 (₱4.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
dbe0a931aef5…Jan 25, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN IV DEO₱4,820,790.87

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AJ0101Aug 6, 2025CONSTRUCTION SLOPE PROTECTION, BRGY. PAYAR, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0120Aug 6, 2025ACCESS ROAD LEADING TO MINOR BASILICA OF SAINT DOMINIC DE GUZMAN, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M
25A00545Jul 4, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. TURAC, CITY OF SAN CARLOS, PANGASINANCompleted₱4.8M
25AJ0100Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL (WATER IMPOUNDING), BRGY. RIZAL, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0102Jun 5, 2025CONSTRUCTION OF DRAINAGE CANAL, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0107Jun 5, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN JUAN RIVER, BARANGAY MESTIZO NORTE, SAN CARLOS CITY, PANGASINANOn-Going₱19.1M
25AJ0124Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANAMINDITAAN CREEK, BARANGAY TALANG, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M
25AJ0125Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.