Project 24AJ0034
DPWH infrastructure contract
Contract ID:
24AJ0034
Fingerprint:
3c1a2a78da8b04…1eb47cbb91 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2024 (2 yrs 8 mo ago) · Target/actual end May 27, 2024
Description:
CONSTRUCTION OF ROAD, BOQUIG-BACAAN, BARANGAY SALINAP, SAN CARLOS CITY, PANGASINAN
Category:
Roads
Implementing office:
DPWH Pangasinan 4th DEO · Region I
Contractor:
5J AND G CONSTRUCTION AND SUPPLY · DPWH contractor code 35366
Contract amount:
₱4,778,619.86 (₱4.8M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 1b7e3561e0a9… | Feb 16, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN IV DEO | ₱4,779,252.61 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AJ0101 | Aug 6, 2025 | CONSTRUCTION SLOPE PROTECTION, BRGY. PAYAR, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0120 | Aug 6, 2025 | ACCESS ROAD LEADING TO MINOR BASILICA OF SAINT DOMINIC DE GUZMAN, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
| 25A00545 | Jul 4, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. TURAC, CITY OF SAN CARLOS, PANGASINAN | Completed | ₱4.8M |
| 25AJ0100 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL (WATER IMPOUNDING), BRGY. RIZAL, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0102 | Jun 5, 2025 | CONSTRUCTION OF DRAINAGE CANAL, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0107 | Jun 5, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN JUAN RIVER, BARANGAY MESTIZO NORTE, SAN CARLOS CITY, PANGASINAN | On-Going | ₱19.1M |
| 25AJ0124 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANAMINDITAAN CREEK, BARANGAY TALANG, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
| 25AJ0125 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.