Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24AJ0044

DPWH infrastructure contract
Contract ID:
24AJ0044
Fingerprint:
036bec3beb9b06…835e60f365 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Feb 23, 2024 (2 yrs 8 mo ago)
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH CENTER), BARANGAY CANAN SUR, MALASIQUI, PANGASINAN
Category:
GAA 2024 SSP
Implementing office:
Contractor:
ROCKWELL CONSTRUCTION AND SUPPLY · DPWH contractor code 43867
Contract amount:
₱6,777,420.29 (₱6.8M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
c0b416d7a80e…Feb 16, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN IV DEO₱6,285,843.77

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AJ0110Jan 8, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDINGS, MUNICIPALITY OF MALASIQUI, PANGASINANOn-Going₱41.6M
25AJ0048Jul 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY LOKEB ESTE, MALASIQUI, PANGASINANCompleted₱4.9M
25AJ0104Jul 14, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, BARANGAY POTIOCAN, MALASIQUI, PANGASINANCompleted₱9.6M
25AJ0122Jul 14, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INGALERA RIVER, BARANGAY TALOSPATANG, MALASIQUI, PANGASINANCompleted₱47.2M
25AJ0139Jul 14, 2025CONSTRUCTION OF ROAD WITH DRAINAGE STRUCTURE, CALLEJON BONIFACIO STREET, BARANGAY POBLACION, MALASIQUI, PANGASINANOn-Going₱4.8M
25AJ0042May 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY NALSIAN NORTE, MALASIQUI, PANGASINANCompleted₱4.9M
25AJ0050May 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BOLAOIT, MALASIQUI, PANGASINANOn-Going₱4.9M
25AJ0058May 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY ASIN EAST, MALASIQUI, PANGASINANOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.