Project 24AJ0049
DPWH infrastructure contract
Contract ID:
24AJ0049
Fingerprint:
dbc134c493ea69…6397486846 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 25, 2024 (2 yrs 7 mo ago) · Target/actual end Jul 17, 2024
Description:
CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN JUAN RIVER, BARANGAY TURAC, SAN CARLOS CITY, PANGASINAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Pangasinan 4th DEO · Region I
Contractor:
EXTENSIVE STEEL WORKS AND CONSTRUCTION · DPWH contractor code 33124
Contract amount:
₱19,197,354.75 (₱19.2M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9ca32d452041… | Mar 15, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN IV DEO | ₱19,160,922.45 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AJ0101 | Aug 6, 2025 | CONSTRUCTION SLOPE PROTECTION, BRGY. PAYAR, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0120 | Aug 6, 2025 | ACCESS ROAD LEADING TO MINOR BASILICA OF SAINT DOMINIC DE GUZMAN, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
| 25A00545 | Jul 4, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. TURAC, CITY OF SAN CARLOS, PANGASINAN | Completed | ₱4.8M |
| 25AJ0100 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL (WATER IMPOUNDING), BRGY. RIZAL, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0102 | Jun 5, 2025 | CONSTRUCTION OF DRAINAGE CANAL, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINAN | On-Going | ₱4.8M |
| 25AJ0107 | Jun 5, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN JUAN RIVER, BARANGAY MESTIZO NORTE, SAN CARLOS CITY, PANGASINAN | On-Going | ₱19.1M |
| 25AJ0124 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANAMINDITAAN CREEK, BARANGAY TALANG, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
| 25AJ0125 | Jun 5, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINAN | On-Going | ₱47.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.