Project 24BA0017
DPWH infrastructure contract
Contract ID:
24BA0017
Fingerprint:
beb68730746a47…f3221dfd0e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 4, 2024 (2 yrs 8 mo ago) · Target/actual end Aug 26, 2024
Description:
OO2 PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS; FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONSTRUCTION OF UYUGAN FLOOD CONTROL (VALUGAN SECTION) PHASE 2, UYUGAN, BATANES
Category:
Flood Control and Drainage
Implementing office:
DPWH Batanes DEO · Region II
Contractor:
J.F. GABOTERO, INC. · DPWH contractor code 49240
Contract amount:
₱9,784,961.17 (₱9.8M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4528c6d8aa86… | Jan 30, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANES DEO | ₱9,784,961.17 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BA0079 | Feb 25, 2026 | REPAIR/ REHABILITATION OF CLASSROOMS, BATANES GEN. COMP. HS, UYUGAN, BATANES | Completed | ₱3.4M |
| 25BA0066 | Jul 25, 2025 | CONSTRUCTION OF SCHOOL BUILDING, ITBUD INTEGRATED SCHOOL, BRGY. ITBUD, UYUGAN, BATANES | On-Going | ₱9.9M |
| 25BA0050 | Jun 18, 2025 | CONCRETING OF GI-ARAÑI - VADINARAN FMR, BRGY. KAYUGANAN, UYUGAN, BATANES | On-Going | ₱14.3M |
| 25BA0040 | Mar 31, 2025 | OO2: PROTECT LIVES AND PROPERTIES AGAINST: MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, DICHOD SECTION, BARANGAY KAYUGANAN, UYUGAN, BATANES | On-Going | ₱19.6M |
| 25BA0010 | Mar 30, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROAD FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES: CONSTRUCTION OF RACUH - AKSUNG ROAD, BARANGAY ITBUD, UYUGAN, BATANES | Completed | ₱5.9M |
| 25BA0023 | Mar 21, 2025 | ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS:FLOOD MANAGEMENT PROGRAM:CONTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS:CONSTRUCTION OF SHORE PROTECTION STRUCTURES ALONG BASCO-ITBUD DIVERSION ROAD | Completed | ₱19.6M |
| 25BA0034 | Mar 21, 2025 | OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS:CONSTRUCTION OF SONGSONG FLOOD CONTROL STRUCTURE,BARANGAY KAYVALUGANAN,UYUGAN, BATANES | Completed | ₱19.6M |
| 25BA0024 | Mar 20, 2025 | ORGANIZATIONALOUTCOME2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS:FLOOD MANAGEMENT PROGRAM:CONTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS:CONSTRUCTION OF SHORE PROTECTION STRUCTURES ALONG BRGY.KAYUGANAN,UYUGAN, BATANES | Completed | ₱19.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.