Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24BF0049

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","24BF0049","ORGANIZATIONAL OUTCOME 2 : FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OFFLOOD MITIGATION FACILITIES WITHIN  MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF MALLIG RIVER  CONTROL PROJECT, BARANGAY BINARZANG PHASE II, STA. 1+100 -STA.","Flood Control and Drainage","Completed",96488743.81,0,100,"Isabela 2nd DEO","Region II","JWU CONSTRUCTION AND SUPPLY (48659)","2024-04-15","2025-05-20",2024,"Regular Infra - GAA 2024 OO-2",17.15377,121.68303,"203123000","203100000"]
SHA-256
7759a61a48face9af68ef38733f5731bea621e7258e86000278452ea4f62f02f

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.