Project 24BF0128
DPWH infrastructure contract
Contract ID:
24BF0128
Fingerprint:
5ba572c6a70bd3…e9c5af2c99 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 30, 2024 (2 yrs ago) · Target/actual end Mar 21, 2025
Description:
COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN JOSE, QUIRINO, ISABELA
Category:
Buildings and Facilities
Implementing office:
DPWH Isabela 2nd DEO · Region II
Contractor:
JWU CONSTRUCTION AND SUPPLY · DPWH contractor code 48659
Contract amount:
₱4,913,476.95 (₱4.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 5fdf9ceb1ceb… | Oct 11, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 2ND DEO | ₱4,913,476.95 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BF0110 | Oct 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LUNA, QUIRINO, ISABELA | Completed | ₱9.6M |
| 25BF0090 | Aug 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, QUIRINO CENTRAL SCHOOL, QUIRINO, ISABELA | Completed | ₱4.8M |
| 25BF0077 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. STO. DOMINGO, QUIRINO, ISABELA | Completed | ₱4.8M |
| 25BF0070 | Jun 30, 2025 | OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF MALLIG RIVER FLOOD CONTROL STRUCTURE (VILLA BULUSAN SECTSECTION), PHASE III, QUIRINO, ISABELA | On-Going | ₱93.6M |
| 25BF0059 | Jun 16, 2025 | OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL STRUCTURE (CULLALABO SUR SECTION), BARANGAY CULLALABO, BURGOS, ISABELA | Completed | ₱140.4M |
| 25BF0014 | Jun 9, 2025 | OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL STRUCTURE, PHASE 3, SAN ANTONINO SECTION, BURGOS, ISABELA | Completed | ₱96.5M |
| 25BF0047 | Jun 9, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BRGY.VINTAR, QUIRINO, ISABELA | On-Going | ₱2.9M |
| 25BF0057 | Jun 9, 2025 | OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL PROJECT, (SAN JOSE SECTION PHASE II) ROXAS, ISABELA | On-Going | ₱93.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.