FY2026 GAA: ₱6.79T
PisoScan

Project 24BH0013

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","24BH0013","ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM  CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BARANGAY PALACIAN FLOOD CO","Flood Control and Drainage","Completed",62722599.34,0,100,"Isabela 4th DEO","Region II","NTL BUILDERS AND DEVELOPER (33450)","2024-03-01","2024-06-18",2024,"Regular Infra - GAA 2024 OO-2",16.40387,121.74195,"203127000","203100000"]
SHA-256
814031cb00e14005c1ba7ea9a73bd268432cf482612aad2980165101976dc0a9

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.