Project 24CC0229
DPWH infrastructure contract
Contract ID:
24CC0229
Fingerprint:
2d1676aa8279f6…25d3b406db Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 14, 2024 (2 yrs 6 mo ago) · Target/actual end Oct 10, 2024
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN MIGUEL, HAGONOY, BULACAN
Category:
Buildings and Facilities
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
TRIPLE O BUILDERS · DPWH contractor code 42161
Contract amount:
₱9,898,960.58 (₱9.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 27a10a8886c8… | May 7, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO | ₱9,701,619.91 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CC0352 | May 23, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN AGUSTIN, HAGONOY, BULACAN | On-Going | ₱9.6M |
| 25CC0480 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY SAN NICOLAS, HAGONOY, BULACAN | On-Going | ₱14.5M |
| 25CC0516 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, EUGENIO G. SY TAMCO ELEMENTARY SCHOOL, HAGONOY, BULACAN | On-Going | ₱14.5M |
| 25CC0538 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN SEBASTIAN, HAGONOY, BULACAN | On-Going | ₱18.4M |
| 25CC0312 | Mar 27, 2025 | CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY SAN AGUSTIN (PARONG PARONG), HAGONOY, BULACAN | On-Going | ₱69.3M |
| 25CC0451 | Mar 27, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CHECK GATE), BARANGAY TAMPOK, AND BARANGAY SANTA MONICA, HAGONOY, BULACAN | On-Going | ₱19.1M |
| 25CC0212 | Mar 21, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN NICOLAS, HAGONOY, BULACAN | On-Going | ₱14.3M |
| 25CC0227 | Mar 21, 2025 | REHABILITATION OF ROAD AT BARANGAY ABULALAS, HAGONOY, BULACAN | On-Going | ₱14.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.