Project 24CC0586
DPWH infrastructure contract
Contract ID:
24CC0586
Fingerprint:
93ad6730468126…c27e67d7ec Verified
Status:
On-Going
Physical progress:
92.9%
Timeline:
Start Dec 17, 2024 (1 yr 10 mo ago)
Description:
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (CONCRETE SLOPE PROTECTION) ALONG LABANGAN CHANNEL AND ITS TRIBUTARIES AT BARANGAY IBA-IBAYO TO BARANGAY ABULALAS, HAGONOY, BULACAN PACKAGE B
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
JTC CRUZ CONSTRUCTION CO. INC. · DPWH contractor code 32479
As listed: JTC CRUZ CONSTRUCTION CO., INC.
Contract amount:
₱92,558,671.69 (₱92.6M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 0d75bfcbaf16… | Dec 16, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO | ₱92,558,671.69 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CC0352 | May 23, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN AGUSTIN, HAGONOY, BULACAN | On-Going | ₱9.6M |
| 25CC0480 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY SAN NICOLAS, HAGONOY, BULACAN | On-Going | ₱14.5M |
| 25CC0516 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, EUGENIO G. SY TAMCO ELEMENTARY SCHOOL, HAGONOY, BULACAN | On-Going | ₱14.5M |
| 25CC0538 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN SEBASTIAN, HAGONOY, BULACAN | On-Going | ₱18.4M |
| 25CC0312 | Mar 27, 2025 | CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY SAN AGUSTIN (PARONG PARONG), HAGONOY, BULACAN | On-Going | ₱69.3M |
| 25CC0451 | Mar 27, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CHECK GATE), BARANGAY TAMPOK, AND BARANGAY SANTA MONICA, HAGONOY, BULACAN | On-Going | ₱19.1M |
| 25CC0212 | Mar 21, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN NICOLAS, HAGONOY, BULACAN | On-Going | ₱14.3M |
| 25CC0227 | Mar 21, 2025 | REHABILITATION OF ROAD AT BARANGAY ABULALAS, HAGONOY, BULACAN | On-Going | ₱14.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.