Project 24CC0642
DPWH infrastructure contract
Contract ID:
24CC0642
Fingerprint:
574207195b7ddb…d82f6ec5b1 Verified
Status:
On-Going
Physical progress:
57.3%
Timeline:
Start Feb 21, 2025 (1 yr 8 mo ago)
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTA MARIA-BOCAUE RIVER, BARANGAY IGULOT (PUROK 3), BOCAUE, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
FLORDES CONSTRUCTION & TRADING CORP. (FORMERLY FLO · DPWH contractor code 16916
Contract amount:
₱77,198,457.05 (₱77.2M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CC0546 | Jun 11, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY BAMBANG, BOCAUE, BULACAN | On-Going | ₱19.3M |
| 25CC0346 | May 23, 2025 | CONSTRUCTION OF CONCRETE REVETMENT STRUCTURE ALONG BOCAUE RIVER BARANGAY BAMBANG SITIO PULO, BOCAUE, BULACAN | On-Going | ₱28.8M |
| 25CC0430 | May 23, 2025 | CONSTRUCTION OF ROAD, BARANGAY TAAL, BOCAUE, BULACAN | On-Going | ₱14.5M |
| 25CC0473 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DUHAT, BOCAUE, BULACAN | On-Going | ₱57.0M |
| 25CC0531 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUNLO, BOCAUE, BULACAN | On-Going | ₱9.7M |
| 25CC0537 | May 23, 2025 | CONSTRUCTION OF DRAINAGE SYSTEMS AT BARANGAY DUHAT, BOCAUE, BULACAN | On-Going | ₱4.8M |
| 25C00178 | Apr 8, 2025 | ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, PROVINCE OF BULACAN | On-Going | ₱68.3M |
| 25CC0337 | Apr 8, 2025 | CONSTRUCTION OF ROAD, BARANGAY LOLOMBOY, BOCAUE, BULACAN | On-Going | ₱14.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.