Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24CE0018

DPWH infrastructure contract
Contract ID:
24CE0018
Fingerprint:
6edb06abc06b85…cf7a0e7c4c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 6, 2024 (2 yrs 9 mo ago) · Target/actual end Aug 12, 2024
Description:
REHABILITATION OF DIKE ALONG TALAVERA RIVER, BARANGAY SAN ANDRES II, QUEZON, NUEVA ECIJA
Category:
Flood Control and Drainage
Implementing office:
Contract amount:
₱95,533,042.22 (₱95.5M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CE0295Jun 2, 2025CONSTRUCTION OF ROAD, BARANGAY SAN JOSE, LICAB, NUEVA ECIJACompleted₱4.9M
25CE0235Apr 2, 2025NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LICAB-VICTORIA RD, NUEVA ECIJACompleted₱33.9M
25CE0265Apr 2, 2025CONSTRUCTION OF ROAD, BARANGAY SANTA MARIA, LICAB, NUEVA ECIJACompleted₱4.9M
25CE0105Mar 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY SANTA LUCIA OLD, ZARAGOZA, NUEVA ECIJACompleted₱48.5M
25CE0019Feb 14, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAINGIN TABING ILOG, GUIMBA, NUEVA ECIJACompleted₱3.0M
25CE0065Feb 14, 2025REHABILITATION OF ROAD, BARANGAY POBLACION SUR, LICAB, NUEVA ECIJACompleted₱10.7M
25CE0072Feb 14, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABONG RIVER, BARANGAY SAN JUAN, LICAB, NUEVA ECIJACompleted₱48.5M
24CE0189Jul 3, 2024NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TALAVERA - LICAB DIVERSION ROAD, NUEVA ECIJACompleted₱19.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.