Project 24CF0039
DPWH infrastructure contract
Contract ID:
24CF0039
Fingerprint:
5a897bde56f8dc…4596683dc3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2024 (2 yrs 9 mo ago) · Target/actual end Nov 25, 2024
Description:
ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CABANATUAN CITY-CARMEN RD - K0127+730-K0127+902, K0128+000-K0128+062
Category:
Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Implementing office:
DPWH Nueva Ecija 2nd DEO · Region III
Contractor:
DGSARM BUILDERS INC. (FORMERLY: D.G. SARMENTA CONSTRUCTION) · DPWH contractor code 13024
Contract amount:
₱11,452,316.14 (₱11.5M)
Funding source:
Regular Infra - Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 89619391851a… | Jan 31, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 2ND DE | ₱11,350,900.17 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0273 | Jul 7, 2025 | CONCRETING OF BRGY. SAN JUAN TO BRGY. UMANGAN FMR, ALIAGA, NUEVA ECIJA | Completed | ₱29.5M |
| 25CE0294 | Jul 1, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY STA. MONICA, ALIAGA, NUEVA ECIJA | Completed | ₱72.1M |
| 25CE0327 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION WEST III, ALIAGA, NUEVA ECIJA | Completed | ₱5.8M |
| 25CE0282 | Jun 2, 2025 | CONSTRUCTION OF SCHOOL BUILDING, ALIAGA CENTRAL SCHOOL, BARANGAY POBLACION CENTRO, ALIAGA, NUEVA ECIJA | Completed | ₱5.0M |
| 25CE0297 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. UMANGAN, ALIAGA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0326 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. POBLACION EAST II, ALIAGA, NUEVA ECIJA | Completed | ₱3.0M |
| 25CE0126 | Apr 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY SAN JUAN, ALIAGA, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0189 | Apr 2, 2025 | CONSTRUCTION OF ROAD INCLUDING DRAINAGE STRUCTURE, BARANGAY BUCOT, ALIAGA, NUEVA ECIJA | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.