Project 24CG0293
DPWH infrastructure contract
Contract ID:
24CG0293
Fingerprint:
eb46a3488fadc6…ddbc2509b4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 12, 2024 (2 yrs 2 mo ago) · Target/actual end Mar 21, 2025
Description:
BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION (REHABILITATION) OF CANDELARIA MULTI-PURPOSE BUILDINGS (COVERED COURT), BRGY. CANDELARIA, MACABEBE, PAMPANGA
Category:
Buildings and Facilities
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
Contract amount:
₱6,563,985.38 (₱6.6M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a40f8abb5cb5… | Sep 5, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 1ST DEO | ₱6,563,985.38 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CG0117 | Jun 11, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY CAMBASI (CENTRO), MASANTOL, PAMPANGA | Completed | ₱56.3M |
| 25CG0126 | Jun 11, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY SAGRADA - BARANGAY NIGUI, MASANTOL, PAMPANGA | Completed | ₱93.8M |
| 25CG0127 | Jun 11, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY BAGANG - BARANGAY BALIBAGO, MASANTOL, PAMPANGA | Completed | ₱93.9M |
| 25CG0086 | Jun 10, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION (COMPLETION) OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY ANAC - STA. LUCIA WAKAS, MASANTOL, PA | Completed | ₱37.5M |
| 25CG0170 | Jun 5, 2025 | CONCRETING OF SITIO MINDANAO, BRGY. ESTEBAN FARM-TO-MARKET ROAD, BRGY. ESTEBAN, MACABEBE, PAMPANGA | Completed | ₱14.1M |
| 25CG0014 | May 22, 2025 | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK AT BARANGAY BEBE ANAC, MASANTOL, PAMPANGA | On-Going | ₱140.4M |
| 25CG0023 | May 22, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF BY-PASS ROAD AND BRIDGE (SAN ESTEBAN) MACABEBE - MALAULI (PHASE IV), MASANTOL, PAMPAN | Completed | ₱44.0M |
| 25CG0111 | Apr 2, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REPAIR / REHABILITATION OF ERODED PAMPANGA RIVER BANK (LANDSLIDE SECTION) (PHASE 1) | Terminated | ₱0 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.