Project 24CJ0375
DPWH infrastructure contract
Contract ID:
24CJ0375
Fingerprint:
9747ee49ed1d5f…75501ad3d0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 17, 2024 (1 yr 10 mo ago) · Target/actual end Feb 17, 2025
Description:
CONSTRUCTION OF ASPHALT OVERLAY ALONG ROMULO H-WAY - K0136 + 148 - K0137 + 232, K0139 + 410 - K0139 + 968
Category:
Roads
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
NORTHERN BUILDERS · DPWH contractor code 8789
Contract amount:
₱94,034,668.88 (₱94.0M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 56a81380745b… | Dec 6, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO | ₱94,034,668.88 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CJ0307 | Aug 11, 2025 | CONSTRUCTION (COMPLETION) OF TARLAC CITY GENERAL HOSPITAL, TARLAC | Completed | ₱78.5M |
| 25CJ0308 | Aug 11, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (TARLAC CITY CONVENTION HALL) BARANGAY BARAS BARAS, TARLAC CITY, TARLAC (PHASE 5) | On-Going | ₱98.2M |
| 25CJ0310 | Aug 11, 2025 | REPAIR/ REHABILITATION/ IMPROVEMENT OF FLOOD CONTROL STRUCTURES ALONG TARLAC RIVER CONTROL SAN ISIDRO, TARLAC CITY, TARLAC | Completed | ₱45.4M |
| 25CJ0306 | Aug 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING TARLAC CITY CONVENTION HALL, BARANGAY BARAS BARAS, TARLAC CITY, TARLAC (PHASE 4) | Completed | ₱98.1M |
| 25CJ0305 | Jul 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (TARLAC CITY CONVENTION HALL), BARANGAY BARAS BARAS, TARLAC CITY, TARLAC (PHASE 7) | Completed | ₱49.0M |
| 25CJ0288 | Jul 11, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (IT CENTER), SAN ISIDRO, TARLAC CITY, TARLAC (ANNEX 4) | On-Going | ₱97.8M |
| 24CJ0414 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, TARLAC CITY GENERAL HOSPITAL, TARLAC CITY, TARLAC | Completed | ₱95.6M |
| 25CJ0304 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BARAS-BARAS, TARLAC CITY, TARLAC (PHASE 3) | Completed | ₱82.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.