Project 24CJ0376
DPWH infrastructure contract
Contract ID:
24CJ0376
Fingerprint:
de325e7de6640f…8667518b67 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 17, 2024 (1 yr 11 mo ago) · Target/actual end Apr 16, 2025
Description:
CONSTRUCTION OF SLOPE PROTECTION WITH STEEL SHEET PILE FOUNDATION ALONG TARLAC RIVER CONTROL, LEFT DIKE, PACKAGE F, STA. MARIA - SAN BARTOLOME SECTION, TARLAC
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
R.R. RICAFORT CONSTRUCTION AND SUPPLIES · DPWH contractor code 14402
Contract amount:
₱99,000,000.00 (₱99.0M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 48a568381fd0… | Dec 6, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO | ₱93,528,345.50 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CJ0236 | Jun 20, 2025 | CONSTRUCTION OF STA. IGNACIA - PANIQUI DIVERSION ROAD (SEGMENT 1), TARLAC | On-Going | ₱95.1M |
| 25CJ0249 | Jun 20, 2025 | CONSTRUCTION OF PARSOLINGAN - BACULONG DIVERSION ROAD (SEGMENT 2), VICTORIA, TARLAC | Completed | ₱96.5M |
| 25CJ0250 | Jun 20, 2025 | CONSTRUCTION OF PARSOLINGAN - BACULONG DIVERSION ROAD (SEGMENT 3), VICTORIA, TARLAC | Completed | ₱96.5M |
| 25CJ0219 | May 16, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALOY RIVER (ANNEX 14), GERONA, TARLAC | On-Going | ₱96.5M |
| 25CJ0183 | Apr 8, 2025 | IMPROVEMENT OF STA. CRUZ - ESTIPONA DIVERSION ROAD (SEGMENT B), TARLAC | On-Going | ₱96.5M |
| 25CJ0193 | Apr 8, 2025 | REHABILITATION OF GERONA ROAD NETWORK (ANNEX 2), GERONA, TARLAC | Completed | ₱72.0M |
| 25CJ0195 | Apr 8, 2025 | REHABILITATION OF ROAD IN APSAYAN, GERONA, TARLAC | Completed | ₱47.9M |
| 25CJ0202 | Apr 8, 2025 | REHABILITATION OF ROAD GOING TO PARSOLINGAN, GERONA, TARLAC | Completed | ₱74.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.