FY2026 GAA: ₱6.79T
PisoScan

Project 24CJ0400

DPWH infrastructure contract
Contract ID:
24CJ0400
Fingerprint:
20987030cdb023…4c7f032ed3 Verified
Status:
On-Going
Physical progress:
87.1%
Timeline:
Start Jan 7, 2025 (1 yr 10 mo ago)
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG DUNGUN CREEK (PACKAGE 24), PANIQUI, TARLAC
Category:
Unprogrammed Appropriations 2024
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
11-16 CONSTRUCTION · DPWH contractor code 29646
Contract amount:
₱98,990,928.00 (₱99.0M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
5548587ebdc7…Dec 26, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO₱93,508,614.25

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26CJ0101Jul 13, 2026PREVENTIVE MAINTENANCE PANIQUI-CAMILING-WAWA RD - K0159 + 904 - K0161 + 250On-Going₱59.4M
26CJ0104Jul 13, 2026PREVENTIVE MAINTENANCE RAMOS-PURA RD - K0157 + 145 - K0158 + 206On-Going₱48.4M
25CJ0168May 16, 2025CONSTRUCTION OF TARLAC RIVER RIGHT ROAD DIKE (SEGMENT 1), MONCADA, TARLACOn-Going₱91.7M
25CJ0189May 16, 2025CONSTRUCTION OF TARLAC RIVER RIGHT ROAD DIKE (SEGMENT 2), MONCADA, TARLACOn-Going₱91.7M
25CJ0200May 16, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TARLAC RIVER, LEFT DIKE, BRILLANTE - ADUAS SECTION (ANNEX 9), PANIQUI, TARLACCompleted₱96.5M
25CJ0218May 16, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTA LUCIA RIVER (ANNEX 8), PANIQUI, TARLACOn-Going₱96.5M
25CJ0160Apr 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BAKA RIVER, PANIQUI, TARLAC (SEGMENT 29)Completed₱74.3M
25CJ0169Apr 8, 2025PREVENTIVE MAINTENANCE MANILA NORTH RD - K0143 + 670 - K0144 + 995Completed₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.