Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24CK0061

DPWH infrastructure contract
Contract ID:
24CK0061
Fingerprint:
265bd6f920b38c…3b5725d55c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 24, 2024 (2 yrs 8 mo ago) · Target/actual end Mar 24, 2024
Description:
INSTALLATION OF SIGNAGE-WARNING, ADVISORY AND REGULATORY SIGNS, PAVEMENT MARKINGS AND STREET LIGHTS ALONG TARLAC - STA. ROSA RD (S01022LZ) - K0133+313 - K0134+310, LA PAZ, TARLAC
Category:
Roads
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
P.C. PANOPIO CONSTRUCTION & TRADING · DPWH contractor code 32824
As listed: P.C. PANOPIO CONSTRUCTION AND TRADING
Contract amount:
₱3,917,487.42 (₱3.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
4a085d50c225…Feb 19, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 2ND-DEO₱3,917,487.42

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CK0082Jun 13, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG THE BANKS OF RIO CHICO RIVER IN BARANGAY LOMBOY (PHASE VII), LA PAZ, TARLACCompleted₱94.7M
25CK0119May 20, 2025CONSTRUCTION OF SCHOOL BUILDING, LAPURISIMA INTEGRATED SCHOOL, LA PAZ, TARLACCompleted₱9.7M
25CK0089Apr 3, 2025REHABILITATION OF ROAD, BARANGAY DUMARAIS - BALANOY, PHASE 1, LA PAZ, TARLACCompleted₱96.5M
25CK0118Apr 3, 2025REHABILITATION OF ROAD AT BARANGAY SAN ROQUE, LA PAZ, TARLACCompleted₱49.0M
25CK0005Mar 25, 2025NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS ALONG VICTORIA - LA PAZ ROAD, K0135 + 075.00 - K0135 + 500.00, LA PAZ, TARLACCompleted₱18.8M
25CK0007Mar 25, 2025ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS ALONG VICTORIA - LA PAZ ROAD, LA PAZ, TARLACOn-Going₱48.0M
25CK0013Mar 25, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PHASE I), LA PAZ, TARLACOn-Going₱69.8M
25CK0014Mar 25, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PHASE II), LA PAZ, TARLACOn-Going₱72.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.