Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24CK0179

DPWH infrastructure contract

This contract as an OC4IDS project record, the infrastructure standard used by OpenGovChain. Download: JSON

{
  "id": "oc4ids-pisoscan-dpwh-24CK0179",
  "title": "CONSTRUCTION OF GROUNDSILL WITH REINFORCED CONCRETE SLOPE PROTECTION ALONG PARUA RIVER, DOWNSTREAM OF SANTA RITA BRIDGE, PHASE 2, CONCEPCION, TARLAC",
  "sector": [
    "Flood Control and Drainage"
  ],
  "status": "completed",
  "publicAuthority": {
    "name": "DPWH Tarlac 2nd DEO"
  },
  "period": {
    "startDate": "2024-12-06",
    "endDate": "2025-06-07"
  },
  "budget": {
    "amount": {
      "amount": 72372314.69,
      "currency": "PHP"
    }
  },
  "locations": [
    {
      "geometry": {
        "type": "Point",
        "coordinates": [
          120.67059,
          15.30459
        ]
      }
    }
  ],
  "parties": [
    {
      "name": "GVDPM CONSTRUCTION CORP. (FORMERLY: ZM CONSTRUCTIO",
      "roles": [
        "supplier"
      ]
    }
  ],
  "contractingProcesses": [
    {
      "id": "24CK0179",
      "summary": {
        "title": "CONSTRUCTION OF GROUNDSILL WITH REINFORCED CONCRETE SLOPE PROTECTION ALONG PARUA RIVER, DOWNSTREAM OF SANTA RITA BRIDGE, PHASE 2, CONCEPCION, TARLAC",
        "status": "closed",
        "contractValue": {
          "amount": 72372314.69,
          "currency": "PHP"
        }
      }
    }
  ],
  "pisoscan": {
    "dpwhStatus": "Completed",
    "physicalProgressPercent": 100,
    "fundingSource": "Outside Infra - Unprogrammed Appropriations 2024",
    "sourceDataset": "DPWH contract list via BetterGov.ph",
    "sha256": "581477ecca4c2a8ae5562434c6d8d4d8e3250204377a138715f6d25e0c8be07c"
  }
}