Project 24CK0179
DPWH infrastructure contract
This contract as an OC4IDS project record, the infrastructure standard used by OpenGovChain. Download: JSON
{
"id": "oc4ids-pisoscan-dpwh-24CK0179",
"title": "CONSTRUCTION OF GROUNDSILL WITH REINFORCED CONCRETE SLOPE PROTECTION ALONG PARUA RIVER, DOWNSTREAM OF SANTA RITA BRIDGE, PHASE 2, CONCEPCION, TARLAC",
"sector": [
"Flood Control and Drainage"
],
"status": "completed",
"publicAuthority": {
"name": "DPWH Tarlac 2nd DEO"
},
"period": {
"startDate": "2024-12-06",
"endDate": "2025-06-07"
},
"budget": {
"amount": {
"amount": 72372314.69,
"currency": "PHP"
}
},
"locations": [
{
"geometry": {
"type": "Point",
"coordinates": [
120.67059,
15.30459
]
}
}
],
"parties": [
{
"name": "GVDPM CONSTRUCTION CORP. (FORMERLY: ZM CONSTRUCTIO",
"roles": [
"supplier"
]
}
],
"contractingProcesses": [
{
"id": "24CK0179",
"summary": {
"title": "CONSTRUCTION OF GROUNDSILL WITH REINFORCED CONCRETE SLOPE PROTECTION ALONG PARUA RIVER, DOWNSTREAM OF SANTA RITA BRIDGE, PHASE 2, CONCEPCION, TARLAC",
"status": "closed",
"contractValue": {
"amount": 72372314.69,
"currency": "PHP"
}
}
}
],
"pisoscan": {
"dpwhStatus": "Completed",
"physicalProgressPercent": 100,
"fundingSource": "Outside Infra - Unprogrammed Appropriations 2024",
"sourceDataset": "DPWH contract list via BetterGov.ph",
"sha256": "581477ecca4c2a8ae5562434c6d8d4d8e3250204377a138715f6d25e0c8be07c"
}
}