Project 24CK0201
DPWH infrastructure contract
Contract ID:
24CK0201
Fingerprint:
d92ad4f74a8c6f…f4050ca395 Verified
Status:
On-Going
Physical progress:
88.0%
Timeline:
Start Jan 4, 2025 (1 yr 10 mo ago)
Description:
REHABILITATION OF DIKE ALONG O'DONNELL RIVER, RIGHT BANK OF BARANGAY LOURDES SECTION, PART B, BAMBAN, TARLAC
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
11-16 CONSTRUCTION · DPWH contractor code 29646
Contract amount:
₱93,121,467.46 (₱93.1M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 8add0d91c3e8… | Dec 27, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 2ND-DEO | ₱93,121,467.46 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26CK0011 | Jun 26, 2026 | ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS ALONG TARLAC - ZAMBALES NORTH WEST DIVERSION ROAD, K0111 + (-312) - K0111 + 790, CAPAS, TARLAC | On-Going | ₱19.8M |
| 25CK0093 | May 20, 2025 | REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT A), CAPAS, TARLAC | Completed | ₱96.5M |
| 25CK0094 | May 20, 2025 | REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT B), CAPAS, TARLAC | Completed | ₱96.5M |
| 25CK0095 | May 20, 2025 | REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT C), CAPAS, TARLAC | Completed | ₱96.5M |
| 25CK0102 | May 20, 2025 | REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT D), CAPAS, TARLAC | Completed | ₱96.5M |
| 25CK0103 | May 20, 2025 | REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT E), CAPAS, TARLAC | Completed | ₱96.5M |
| 25CK0104 | May 20, 2025 | REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER RIGHT SIDE (SEGMENT A), CAPAS, TARLAC | Completed | ₱96.5M |
| 25CK0105 | May 20, 2025 | REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER RIGHT SIDE (SEGMENT B), CAPAS, TARLAC | On-Going | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.