FY2026 GAA: ₱6.79T
PisoScan

Project 24DD0169

DPWH infrastructure contract
Contract ID:
24DD0169
Fingerprint:
0a3971f0fa7501…65bba24fb9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 25, 2024 (2 yrs 6 mo ago) · Target/actual end Aug 20, 2024
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, MUNICIPALITY OF SAN JUAN, BATANGAS
Category:
Roads
Implementing office:
DPWH Batangas 4th DEO · Region IV-A
Contractor:
ALPHA VECTOR CONSTRUCTION AND SUPPLY · DPWH contractor code 44630
Contract amount:
₱9,603,415.00 (₱9.6M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
b9855e5dead4…Apr 15, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANGAS IV DEO₱9,603,415.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25D00017May 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADSSAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 4, SAN JUAN BATANGASOn-Going₱89.4M
25D00018Apr 10, 2025CONSTRUCTION OF REVETMENT ALONG MALAKING ILOG RIVER, PHASE 1, BARANGAY MARAYKIT, SAN JUAN, BATANGASOn-Going₱94.1M
25D00027Apr 10, 2025WIDENING OF PERMANENT BRIDGES BANTILAN BR. (B02946LZ) ALONG SN JUAN-CANDELARIA JCT-CANDELARIA-BOLBOC RDOn-Going₱34.7M
25D00128Apr 10, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MALAKING TUBIG RIVER, PHASE 3, TIAONG, QUEZONOn-Going₱95.1M
25D00016Apr 4, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 3, SAN JUAN BATANGASOn-Going₱230.5M
25D00054Apr 4, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD), BATANGASOn-Going₱47.0M
24DD0300Mar 27, 2025CONCRETING OF BARANGAY PULANGBATO FMR, BARANGAY PULANGBATO, SAN JUAN, BATANGASOn-Going₱19.3M
24DD0303Mar 27, 2025CONCRETING OF BARANGAY SAMPIRO FMR, BARANGAY SAMPIRO, SAN JUAN, BATANGASOn-Going₱14.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.