Project 24DE0020
DPWH infrastructure contract
Contract ID:
24DE0020
Fingerprint:
86afe067db167e…5bbfa1537e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 7, 2024 (2 yrs 9 mo ago) · Target/actual end Jul 2, 2024
Description:
ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HAGONOY RIVER, SAN PASCUAL,
Category:
Flood Control and Drainage
Implementing office:
DPWH Batangas 2nd DEO · Region IV-A
Contractor:
N.D.M. SANCHEZ BUILDERS & DEVELOPMENT CORPORATION · DPWH contractor code 35410
Contract amount:
₱28,950,000.00 (₱28.9M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7421fbbc46e6… | Jan 30, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANGAS 2ND ED | ₱28,513,037.14 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DE0062 | Jun 9, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) PHASE 3, BARANGAY LAUREL, SAN PASCUAL, BATANGAS | Completed | ₱9.9M |
| 25DE0085 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONCRETING OF ROAD, BARANGAY NATUNUAN NORTH, SAN PASCUAL, BATANGAS | Completed | ₱4.8M |
| 25DE0090 | May 27, 2025 | CONVERGENCE AND SPECIAL PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MALAKING POOK MULTI-PURPOSE BUILDING (COVERED COURT) SAN PASCUAL, BATANGAS | On-Going | ₱4.8M |
| 25DE0115 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION MULTI-PURPOSE BUILDING (DAY CARE CENTER) AT BARANGAY GELERANG KAWAYAN, SAN PASCUAL, BATANGAS | Completed | ₱9.9M |
| 25DE0137 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY ALALUM, SAN PASCUAL BATANGAS | On-Going | ₱3.8M |
| 25DE0156 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAYCARE CENTER) AT BRGY. PADRE CASTILLO, SAN PASCUAL, BATANGAS | Completed | ₱7.9M |
| 25DE0174 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SYSTEM AT BARANGAY GELERANG KAWAYAN, SAN PASCUAL, BATANGAS | On-Going | ₱4.8M |
| 25DE0139 | May 26, 2025 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN DIVERSION ROAD, PACKAGE P, BATANGAS | On-Going | ₱36.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.