Project 24DK0062
DPWH infrastructure contract
Contract ID:
24DK0062
Fingerprint:
bfd3d049b42d16…16c4351e33 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 23, 2024 (2 yrs 6 mo ago) · Target/actual end Aug 20, 2024
Description:
CAPITAL OUTLAY - BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN MAGSIKAP INTEGRATED SCHOOL (FORMERLY MAGSIKAP E/S), BARANGAY MAGSIKAP, GENERAL NAKAR, QUEZON
Category:
Buildings and Facilities
Implementing office:
DPWH Quezon 1st DEO · Region IV-A
Contractor:
F.M. PUJEDA BUILDERS AND CONSTRUCTION SUPPLIES · DPWH contractor code 34706
Contract amount:
₱4,974,973.10 (₱5.0M)
Funding source:
Outside Infra - GAA 2024 DepEd BEFF
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d13842c6f098… | Apr 16, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 1ST ED | ₱4,875,226.46 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25D00256 | Jun 9, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE Z, GENERAL NAKAR, QUEZON | On-Going | ₱93.6M |
| 25D00215 | Jun 3, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, INFANTA, QUEZON, PACKAGE R | On-Going | ₱187.2M |
| 25DK0037 | Jun 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MAIGANG, GENERAL NAKAR, QUEZON | On-Going | ₱4.8M |
| 25D00014 | Apr 10, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE T, GENERAL NAKAR, QUEZON | On-Going | ₱94.0M |
| 25DK0051 | Apr 7, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY UMIRAY, GENERAL NAKAR, QUEZON | On-Going | ₱4.8M |
| 25D00008 | Mar 6, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE U, GENERAL NAKAR, QUEZON, PHASE 2 | On-Going | ₱188.2M |
| 25D00009 | Mar 6, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE V, GENERAL NAKAR, QUEZON | On-Going | ₱140.7M |
| 25D00010 | Mar 6, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE W, GENERAL NAKAR, QUEZON | On-Going | ₱140.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.