Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24DM0074

DPWH infrastructure contract
Contract ID:
24DM0074
Fingerprint:
3650ba294bf649…94b534d83c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 7, 2024 (2 yrs 9 mo ago) · Target/actual end Jun 5, 2024
Description:
INSTALLATION OF ROAD SAFETY DEVICES, ROAD SIGNS AND PAVEMENT MARKINGS ALONG SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0312 + 812 - K0321 + 005, K0322 + (-955) - K0327 + 000, SAN FRANCISCO, QUEZON
Category:
Roads
Implementing office:
DPWH Quezon 3rd DEO · Region IV-A
Contractor:
Contract amount:
₱14,700,000.00 (₱14.7M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
9912d096fd85…Jan 26, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 3RD ED₱14,273,722.96

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DM0180Jan 14, 2026CONSTRUCTION OF CLASSROOMS, BUTANGUIAD ELEMENTARY SCHOOL, SAN FRANCISCO, QUEZONCompleted₱5.0M
25DM0185Jan 12, 2026CONSTRUCTION OF CLASSROOMS, MABUNGA NHS, SAN FRANCISCO, QUEZONOn-Going₱15.0M
25DM0170Nov 13, 2025CONSTRUCTION OF QUEZON PROVINCIAL HOSPITAL NETWORK - SAN FRANCISCO (PHASE 3), QUEZONOn-Going₱93.5M
25DM0162Aug 18, 2025CONSTRUCTION OF SCHOOL BUILDING, MARCIAL B. VILLANUEVA NATIONAL HIGH SCHOOL, BARANGAY CAWAYAN 1, SAN FRANCISCO, QUEZONCompleted₱5.0M
25DM0164Aug 18, 2025CONSTRUCTION OF SCHOOL BUILDING, YUGNO ELEMENTARY SCHOOL, SITIO YUGNO, BARANGAY CAMFLORA, SAN ANDRES, QUEZONCompleted₱5.0M
25DM0091Jul 11, 2025CONSTRUCTION OF SMALL RIVER IMPROVEMENT PROJECT, CASAY SIS, SAN FRANCISCO, QUEZONOn-Going₱14.7M
25DM0079Jun 25, 2025CONSTRUCTION OF ROAD, BARANGAY ILAYANG TAYUMAN, SAN FRANCISCO, QUEZONOn-Going₱19.6M
25DM0115Jun 3, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0345 + 000 - K0347 + 000Completed₱93.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.