Project 24DQ0014
DPWH infrastructure contract
Contract ID:
24DQ0014
Fingerprint:
02a345db72b6d6…c0fe3770d2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 13, 2024 (2 yrs 8 mo ago) · Target/actual end Aug 24, 2024
Description:
CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0016 + 902 - K0017 + 454
Category:
Roads
Implementing office:
DPWH Cavite 3rd DEO · Region IV-A
Contractor:
R.K.F. BUILDERS · DPWH contractor code 34344
Contract amount:
₱12,355,182.54 (₱12.4M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7efbbf8de82c… | Feb 13, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE 3RD DISTRIC | ₱12,355,182.54 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DQ0110 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIKSI 2, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DQ0111 | Jul 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DF0158 | Jul 1, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITESCONSTRUCTION OF ROAD WITH DRAINAGE AT BRGY. PALICO IV, CITY OF IMUS, | On-Going | ₱4.8M |
| 25DQ0084 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 1, CITY OF BACOOR, CAVITE | On-Going | ₱96.0M |
| 25DQ0085 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 2, CITY OF BACOOR, CAVITE | On-Going | ₱98.0M |
| 25DQ0090 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 1) | On-Going | ₱98.0M |
| 25DQ0099 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 3) | On-Going | ₱98.0M |
| 25DQ0101 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 2) | On-Going | ₱98.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.