Project 24F00121
DPWH infrastructure contract
Contract ID:
24F00121
Fingerprint:
83b22095d6566e…6e123aeef6 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Apr 19, 2024 (2 yrs 6 mo ago)
Description:
ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY PACKAGE 14, CAMARINES SUR, MINALABAC, CAMARINES SUR (2ND LEGISLATIVE DISTRICT)
Category:
GAA 2024 OO-1
Implementing office:
DPWH Region V · Region V
Contractor:
G.C.I. CONSTRUCTION AND DEV'T. CORP. · DPWH contractor code 11346
Contract amount:
₱192,999,724.26 (₱193.0M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FE0032 | Jun 20, 2025 | CONSTRUCTION/REHABILITATION OF RAINWATER COLLECTORS SYSTEM (RWCS) IN PUBLIC FACILITIES 1) MALBONG ELEMENTARY SCHOOL, BRGY. MALBONG, GAINZA, CAMARINES SUR 2) CAGBUNGA ELEMENTARY SCHOOL, BRGY. CAGBUNGA, GAINZA, CAMARINES SUR 3) DAHILIG ELEMENTARY SCHOOL, BR | Completed | ₱2.6M |
| 25F00222 | Jun 11, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CAMARINES SUR EXPRESSWAY PACKAGE 17, CAMARINES SUR, MINALABAC, CAMARINES SUR (2ND LEGISLATIVE DISTRICT) | On-Going | ₱190.1M |
| 25F00223 | Jun 5, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY PACKAGE 18, CAMARINES SUR, MINALABAC, CAMARINES SUR (2ND LEGISLATIVE DISTRICT) | On-Going | ₱190.1M |
| 24FE0070 | Mar 24, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BICOL RIVER (UPSTREAM, LEFTSIDE), BARANGAY BALIUAG VIEJO, MINALABAC, CAMARINES SUR | Completed | ₱47.8M |
| 25FE0014 | Mar 7, 2025 | OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BICOL RIVER (DOWNSTREAM), BARANGAY BALIUAG NUEVO, MINALABAC, CAMA | On-Going | ₱62.1M |
| 24FN0092 | Feb 14, 2025 | OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD CONTROL STRUCT., BICOL RIVER REV'T WALL, BRGY. SAN RAMON SEC., BULA, CAMSUR | On-Going | ₱144.8M |
| 24FE0062 | Oct 7, 2024 | CSSP: BASIC INFRASTRUTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SITIO GILID, BARANGAY TARIRIC, MINALABAC, CAMARINES SUR (REBIDDING) | Completed | ₱2.0M |
| 24FE0058 | Jun 19, 2024 | CONCRETING OF BRGY. TARIRIC, MINALABAC, CAMARINES SUR | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.