Project 24F00441
DPWH infrastructure contract
Contract ID:
24F00441
Fingerprint:
89a5a198b53c1d…2eaeab7631 Verified
Status:
On-Going
Physical progress:
92.8%
Timeline:
Start Dec 27, 2024 (1 yr 10 mo ago)
Description:
CAPITAL OUTLAY - DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) - LGU HOSPITALS-CAMARINES NORTE PROVINCIAL HOSPITAL, CAMARINES NORTE, DAET, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT)
Category:
GAA 2024 DOH HFEP
Implementing office:
DPWH Region V · Region V
Contractor:
HGG BUILDERS & SUPPLY (17824) / IA FERRER CONSTRUCTION & SUPPLY · DPWH contractor code 34709
Contract amount:
₱39,799,291.46 (₱39.8M)
Funding source:
Outside Infra - GAA 2024 DOH HFEP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25F00487 | Jul 18, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, DAET, CAMARINES NORTE, DAET, CAMARINES NORTE | On-Going | ₱9.6M |
| 25F00440 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MENRO OFFICE, ELEVATED PLAZA, BARANGAY VI(POBLACION), DAET, C | On-Going | ₱2.8M |
| 24F00331 | Apr 3, 2025 | CONCRETING OF BRGY. II, FMR BRGY. II, DAET, CAMARINES NORTE, DAET, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) | On-Going | ₱9.9M |
| 24F00487 | Apr 3, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-REHABILITATION OF MULTI-PURPOSE BUILDING (CAMARINES NORTE AGRO MULTI-PURPOSE COMPLEX CUM EVACUATION CENTER), BARAN | On-Going | ₱99.0M |
| 24F00499 | Apr 3, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY MAGANG DA | Completed | ₱4.7M |
| 24F00500 | Apr 3, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, MENRO BUILDING ELEVATED PLAZA PHASE 1, BARANGAY 6, DAET, CAMARINES NORTE, | Completed | ₱4.8M |
| 24F00503 | Apr 3, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, MANCRUZ ELEMENTARY SCHOOL, BARANGAY MANCRUZ, DAET, CAMARINES NORTE, DAET, | Completed | ₱4.8M |
| 24F00504 | Apr 3, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, MANTAGBAC ELEMENTARY SCHOOL, BARANGAY MANTAGBAC, DAET, CAMARINES NORTE, DA | On-Going | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.