Project 24GA0053
DPWH infrastructure contract
Contract ID:
24GA0053
Fingerprint:
f706bd7b8e69d0…912c00eef6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 6, 2024 (2 yrs 9 mo ago) · Target/actual end Apr 15, 2024
Description:
CONSTRUCTION (COMPLETION) OF MPB BRGY. CALANGCANG, MAKATO, AKLAN
Category:
Buildings and Facilities
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
J.C. TAMAYO ENTERPRISES · DPWH contractor code 39862
Contract amount:
₱1,958,294.12 (₱2.0M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 1e600de150a1… | Jan 29, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO | ₱1,958,294.12 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0138 | Sep 16, 2025 | CONCRETING OF SITIO LIONG, BRGY. CALIMBAJAN FMR, MAKATO, AKLAN | On-Going | ₱11.9M |
| 25GA0134 | Jul 10, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAKATO RIVER (MAKATO BYPASS ROAD), BARANGAY POBLACION, MAKATO, AKLAN | On-Going | ₱86.2M |
| 25GA0011 | Jun 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALANGCANG, MAKATO, AKLAN | On-Going | ₱86.4M |
| 25GA0093 | Jun 4, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TINA, MAKATO, AKLAN | Completed | ₱2.0M |
| 25GA0118 | Jun 4, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY CABATANGA, MAKATO, AKLAN | Completed | ₱3.0M |
| 25GA0094 | Jun 3, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, (MAKATO PUBLIC MARKET), BARANGAY POBLACION, MAKATO, AKLAN | Completed | ₱7.9M |
| 25GA0106 | Jun 3, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, (MAKATO INTEGRATED SCHOOL), BARANGAY POBLACION, MAKATO, AKLAN | Completed | ₱2.0M |
| 25GA0092 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BAGONG BARRIO, MAKATO, AKLAN | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.