Project 24GF0079
DPWH infrastructure contract
Contract ID:
24GF0079
Fingerprint:
0c4c401f540de6…ffc0aa795b Verified
Status:
On-Going
Physical progress:
90.2%
Timeline:
Start Apr 29, 2024 (2 yrs 6 mo ago)
Description:
CONSTRUCTION OF SIBALOM RIVER FLOOD CONTROL PROJECT, TIGBAUAN, ILOILO
Category:
GAA 2024 OO-2
Implementing office:
DPWH Iloilo 1st DEO · Region VI
Contractor:
A.D. PENDON CONSTRUCTION & SUPPLY, INC. (FORMERLY: ADP CONSTRUCTION & SUPPLY) · DPWH contractor code 3466
Contract amount:
₱37,142,633.12 (₱37.1M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GF0118 | Oct 24, 2025 | CONSTRUCTION OF SCHOOL BUILDING, TIGBAUAN NATIONAL HIGH SCHOOL, TIGBAUAN, ILOILO | On-Going | ₱59.7M |
| 25GF0096 | Jun 16, 2025 | CONSTRUCTION OF CORDOVA - BAROSONG BRIDGE, TIGBAUAN, ILOILO | On-Going | ₱48.1M |
| 25GF0010 | Jun 3, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG ILOILO-ANTIQUE RD - K0021+000 - K0022+751 | On-Going | ₱9.7M |
| 25GF0048 | Jun 3, 2025 | ROAD WIDENING- ILOILO-ANTIQUE RD -K0023+734 - K0023+757, K0023+912 - K0024+079, K0024+079 - K0024+123 | Completed | ₱8.8M |
| 25GF0089 | Jun 3, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, TIGBAUAN, ILOILO | On-Going | ₱139.8M |
| 25GF0101 | Jun 3, 2025 | CONCRETING OF BRGY. BITAS FMR, BRGY. BITAS, TIGBAUAN, ILOILO | Completed | ₱14.9M |
| 25GF0102 | Jun 3, 2025 | CONCRETING OF BRGY. OLO BARROC FMR, BRGY. OLO BARROC, TIGBAUAN, ILOILO | Completed | ₱14.9M |
| 25GF0103 | Jun 3, 2025 | CONCRETING OF SITIO HATOL TO SITIO KATIKLAN, BRGY. NANGA FMR, BRGY. NANGA, GUIMBAL, ILOILO | On-Going | ₱14.9M |