Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24GH0109

DPWH infrastructure contract
Contract ID:
24GH0109
Fingerprint:
cb55b7d102c6e0…bdbffca77f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 8, 2024 (2 yrs 7 mo ago) · Target/actual end Nov 29, 2024
Description:
OFF CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS- PASSI- SAN RAFAEL- LEMERY- SARA RD- K0078+553- K0078+587, K0078+634- K0078+885, K0079+000- K0079+071, K0079+154- K0080+891, K0080+1014- K0081+219, K0080+891- K0080+1014
Category:
Roads
Implementing office:
DPWH Iloilo 3rd DEO · Region VI
Contract amount:
₱31,657,920.00 (₱31.7M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GH0151Mar 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING BARANGAY SINCUA, LEMERY, ILOILOCompleted₱2.0M
25GH0139Mar 25, 2025CONSTRUCTION OF CONCRETE ROAD- CONSTRUCTION OF ROAD, BARANGAY NASAPAHAN, LEMERY, ILOILOCompleted₱9.7M
25GH0087Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY YAWYAWAN, LEMERY, ILOILOCompleted₱3.9M
25GH0092Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN JOSE, LEMERY, ILOILOCompleted₱4.0M
25GH0051Feb 19, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- PASSI- SAN RAFAEL- LEMERY- SARA RD- K0081+430- K0082+580On-Going₱48.2M
25GH0053Feb 19, 2025RECONSTRUCTION TO CONCRETE PAVEMENT- PASSI- SAN RAFAEL- LEMERY- SARA RD K0086+805- K0086+938, K0086+943- K0087+507Completed₱18.5M
25GH0071Feb 19, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- PASSI- SN RAFAEL- LEMERY- SARA RD- K0082+625- K0082+650Completed₱2.0M
25GH0081Feb 19, 2025REHABILITATION/ MAJOR REPAIR OF BRIDGE - GERONGAN BR. (B00225PN) ALONG PASSI-SN RAFAEL-LEMERY-SARA RDOn-Going₱25.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.