DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","24HA0002","CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF VILLANUEVA, TUBIGON, FLOOD CONTROL, TUBIGON, BOHOL","Flood Control and Drainage","Completed",52974619.82,0,100,"Bohol 1st DEO","Region VII","N.N. YU CONSTRUCTION, INC. (FORMERLY: YU CONSTRUCTION) (10470)","2024-04-11","2024-10-17",2024,"Regular Infra - GAA 2024 OO-2",9.91029,123.93356,"701245000","701200000"]
SHA-256
95dc6ef76cc8c8c92acb42e18af526a72971f81bcfe6740695e4a42c1bc584f9

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.