Project 24HA0108
DPWH infrastructure contract
Contract ID:
24HA0108
Fingerprint:
9550850c693986…bd21e6892a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 15, 2024 (2 yrs 5 mo ago) · Target/actual end Sep 11, 2024
Description:
CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN LIBAONG ELEMENTARY SCHOOL, BARANGAY LIBAONG, PANGLAO, BOHOL
Category:
Buildings and Facilities
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
EFB CONSTRUCTION SERVICES · DPWH contractor code 46194
Contract amount:
₱4,973,741.35 (₱5.0M)
Funding source:
Outside Infra - GAA 2024 DepEd BEFF
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b20cff8d1b06… | Apr 29, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 1ST ED | ₱4,973,741.35 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0102 | Jun 2, 2025 | CONSTRUCTION OF ROAD, BRGY. LOURDES TO BRGY. TANGNAN, PANGLAO, BOHOL | Completed | ₱29.0M |
| 25HA0058 | May 30, 2025 | COMPLETION OF MULTI-PURPOSE BUILDINGS (LIBAONG, POBLACION), PANGLAO, BOHOL | Completed | ₱5.9M |
| 25HA0001 | Feb 12, 2025 | PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT (TER) DAUIS-PANGLAO RD - K0013 + 533 - K0014 + 000, K0016 + 000 - K0017 + 000 | Completed | ₱46.7M |
| 23HA0171 | Jan 10, 2025 | CONSTRUCTION OF BOHOL CONVENTION CENTER, BOHOL | On-Going | ₱49.3M |
| 24HA0083 | Apr 12, 2024 | IMPROVEMENT OF INTERSECTION - JCT. (TER) DAUIS-PANGLAO RD (S0021BH) AND PANGLAO ISLAND CIRCUMFERENTIAL RD (S0064BH) - K0017+800, POBLACION, PANGLAO, BOHOL | Completed | ₱1.6M |
| 24HA0007 | Feb 12, 2024 | PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT (TER) DAUIS-PANGLAO RD - K0013+400 - K0013+484 | Completed | ₱3.0M |
| 24HA0011 | Feb 12, 2024 | CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - JCT. PICR VIA BIKING-LIBAONG-BOLOD ACCESS ROADS LEADING TO NEW BOHOL-PANGLAO INTERNATION AIRPORT, PANGLAO, BOHOL | Completed | ₱6.6M |
| 23HA0002 | May 25, 2023 | PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT (TER) DAUIS-PANGLAO RD - K0007 + 750 - K0008 + 000, K0011 + 842.40 - K0013+400 | Completed | ₱56.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.