Project 24HD0004
DPWH infrastructure contract
Contract ID:
24HD0004
Fingerprint:
126cc7918af82c…7fb2377e12 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2024 (2 yrs 9 mo ago) · Target/actual end Jul 11, 2024
Description:
CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT MAGSA-UBAY BRIDGE, DAANBANTAYAN, CEBU
Category:
Flood Control and Drainage
Implementing office:
DPWH Cebu 4th DEO · Region VII
Contractor:
TCP BUILDERS · DPWH contractor code 40000
Contract amount:
₱29,400,000.00 (₱29.4M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 49fa7c8c7a40… | Jan 29, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CEBU 1ST DEO | ₱29,105,924.65 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HG0085 | May 19, 2025 | CONSTRUCTION OF SPECIAL SCIENCE BUILDING, DAANBANTAYAN NATIONAL HIGH SCHOOL, POBLACION, DAANBANTAYAN, CEBU | Completed | ₱4.9M |
| 25HG0023 | Feb 27, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BATERIA, DAANBANTAYAN, CEBU | Completed | ₱4.9M |
| 25HG0043 | Feb 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, DAANBANTAYAN, CEBU | Completed | ₱9.6M |
| 25HG0045 | Feb 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TAPILON, DAANBANTAYAN, CEBU | Completed | ₱4.9M |
| 24HD0123 | Aug 22, 2024 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM; 1)TABOGON, CEBU 2) DAANBANTAYAN, CEBU 3) SANTA FE, CEBU 4) SAN REMIGIO, CEBU | Completed | ₱2.9M |
| 24HD0117 | Aug 12, 2024 | SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DRAINAGE OUTFALL AT BOGO-CURVA-MEDELLIN-DAANBANTAYAN-MAYA ROAD, BARANGAY AGUJO, DAANBANTAYAN, CEBU | Completed | ₱19.6M |
| 24HD0107 | Jul 8, 2024 | SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DRAINAGE OUTFALL AT BARANGAY, POBLACION, DAANBANTAYAN, CEBU | Completed | ₱19.6M |
| 24HD0088 | Jun 17, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAYPAY, DAANBANTAYAN, CEBU | Completed | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.