Project 24IE0071
DPWH infrastructure contract
Contract ID:
24IE0071
Fingerprint:
ad2f4e2ef71072…ed495293d9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 9, 2024 (2 yrs 2 mo ago) · Target/actual end Oct 10, 2024
Description:
CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), SAN FRANCISCO ELEMENTARY SCHOOL AND CAHIGAN NATIONAL HIGH SCHOOL, VILLABA, LEYTE, MATALOTO ELEMENTARY SCHOOL, BAGABAO PRIMARY SCHOOL AND LEYTE NATIONAL HIGH SCHOOL, LEYTE, LEYTE
Category:
Water Provision and Storage
Implementing office:
DPWH Leyte 3rd DEO · Region VIII
Contractor:
KAUIE BUILDERS & SUPPLIES INC. (FORMERLY: KAUIE BUILDERS AND CONSTRUCTION SUPPLIES) · DPWH contractor code 33841
Contract amount:
₱1,597,204.28 (₱1.6M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IE0010 | Jun 28, 2026 | BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES, LIBAS BR. (B00088LT) ALONG LEMON-LEYTE-BILIRAN RD., BARANGAY LIBAS, LEYTE, LEYTE | On-Going | ₱23.1M |
| 25IE0096 | Aug 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), LEYTE AGRO-INDUSTRIAL SCHOOL, LEYTE, LEYTE | On-Going | ₱322.4K |
| 25IE0097 | Aug 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), WAGUE ELEMENTARY SCHOOL, LEYTE, LEYTE | On-Going | ₱322.2K |
| 25IE0098 | Aug 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), DOÑA GLECERIA MUERTIGUI ELEMENTARY SCHOOL, LEYTE, LEYTE | On-Going | ₱322.2K |
| 25IE0074 | Jun 29, 2025 | CONCRETING OF SITIO RIMAS TO BRGY. PARARAO FMR, LEYTE, LEYTEBRGY. PARARAO, LEYTE, LEYTE | On-Going | ₱14.9M |
| 25IE0057 | Jun 5, 2025 | ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CABUNGA-AN TABUNOK - CONSUEGRA RD. K1030+600-K1031+000, LEYTE,LEYTE | On-Going | ₱96.4M |
| 25IE0078 | Jun 5, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BURABOD, LEYTE, LEYTE | Completed | ₱2.0M |
| 25IE0086 | Jun 5, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SB BUILDING), BARANGAY VELOSO, CALUBIAN, LEYTE | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.