Project 24IF0061

DPWH infrastructure contract
Contract ID:
24IF0061
Fingerprint:
01041d0912fdb4…8bd93f1706 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 14, 2024 (2 yrs 7 mo ago) · Target/actual end Oct 18, 2024
Description:
CONSTRUCTION OF BENOLHO FLOOD CONTROL STRUCTURE (UPSTREAM), ALBUERA, LEYTE
Category:
Flood Control and Drainage
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contract amount:
₱96,399,778.30 (₱96.4M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26IF0039Aug 10, 2026ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - ORMOC-BAYBAY- SOUTHERN LEYTE BDRY. RD. - K1034+082 - K1034+265, K1034+340 - K1034+806On-Going₱41.2M
26IF0033Jul 27, 2026ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - ORMOC-BAYBAY-SOUTHERN LEYTE BDRY. RD. - K1035+045 - K1035+510, K1037+124 - K1037+246On-Going₱31.3M
25IF0097Aug 27, 2025CONSTRUCTION/REHABILITATION OF RAINWATER COLLECTORS SYSTEM (RWCS), SALVACION ELEMENTARY SCHOOL, BRGY. SALVACION, ALBUERA, LEYTE; DOÑA MARIA ELEMENTARY SCHOOL, BRGY. DOÑA MARIA, ALBUERA, LEYTE; ALBUERA SOUTH CENTRAL SCHOOL, BRGY. DAMULAAN, ALBUERA, LEYTE;Completed₱2.6M
25IF0093Aug 4, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY DAMULAAN, ALBUERA, LEYTECompleted₱4.9M
25IF0014Mar 26, 2025CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE CAGBULO RIVER, ALBUERA, LEYTECompleted₱48.1M
25IF0047Mar 19, 2025ASSET PRESERVATION - PREVENTIVE MAINTENANCE- PRIMARY ROADS - ORMOC - BAYBAY - SOUTHERN LEYTE BDRY RD - K1031+785 - K1032+129Completed₱21.2M
25IF0069Mar 19, 2025CONSTRUCTION OF ROAD, POBLACION, ALBUERA, LEYTECompleted₱18.6M
25IF0057Mar 4, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG ALBUERA-DIVERSION ROAD, ALBUERA, LEYTECompleted₱48.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.