Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24IG0039

DPWH infrastructure contract
Contract ID:
24IG0039
Fingerprint:
234f373be40d72…8472b7596a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 18, 2024 (2 yrs 7 mo ago) · Target/actual end Sep 18, 2024
Description:
NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BATO BY-PASS ROAD, LEYTE
Category:
Roads
Implementing office:
DPWH Leyte 5th DEO · Region VIII
Contractor:
C N E CONSTRUCTION · DPWH contractor code 22148
Contract amount:
₱37,820,748.00 (₱37.8M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26IG0019Jul 27, 2026CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BATO BY-PASS ROAD, STA. 2+233 - 2+513, BARANGAY TABUNOK, LEYTEOn-Going₱33.0M
25IG0010Jun 3, 2025CONSTRUCTION OF ROAD, SITIO KAMANGGAHAN, BARANGAY BAGO, BATO, LEYTECompleted₱4.9M
25IG0065Jun 3, 2025NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BATO-BONTOC RD - K1117 + 879 - K1120+000On-Going₱77.2M
25IG0040May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TABUNOK, BATO, LEYTECompleted₱4.9M
25IG0055May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ANAHAWAN, BATO, LEYTECompleted₱3.0M
25IG0063May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KALANGGAMAN, BATO, LEYTECompleted₱4.9M
25IG0016Mar 27, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BATO BY-PASS ROAD, LEYTECompleted₱19.6M
25IG0014Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY TAGAYTAY, BATO, LEYTECompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.