Project 24J00042
DPWH infrastructure contract
Contract ID:
24J00042
Fingerprint:
4a85342b3c385f…d258eeaa5b Verified
Status:
On-Going
Physical progress:
90.4%
Timeline:
Start Feb 29, 2024 (2 yrs 8 mo ago)
Description:
CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASIN AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SIBUGUEY RIVER, SIBUGUEY BR. SECTION (B00480MN) ALONG LANAO-PAGADIAN-ZAMBOANGA CITY ROAD (S01112MN) RIGHT
Category:
Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP
Implementing office:
DPWH Region IX · Region IX
Contractor:
DL ENTERPRISES · DPWH contractor code 18155
Contract amount:
₱146,153,379.64 (₱146.2M)
Funding source:
Regular Infra - Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 163cc4220ee2… | Feb 27, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IX | ₱146,153,379.64 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JI0026 | Jun 26, 2025 | CONSTRUCTION OF ROAD, NATIONAL ROAD JCT. BARANGAY LOWER BALURAN LEADING TO BARANGAY MT. VIEW TO BARANGAY LUMPANAC CONNECTING NATIONAL ROAD JCT. BARANGAY GANDIANGAN ROAD, IMELDA, ZAMBOANGA SIBUGAY | On-Going | ₱14.7M |
| 25JI0005 | Jun 18, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - LOWER BALURAN - DUMPOC DIVERSION ROAD, ZAMBOANGA SIBUGAY | On-Going | ₱55.0M |
| 25JI0083 | May 28, 2025 | CONCRETING OF BRGY. LUMBOG FMR, BRGY. LUMBOG, IMELDA, ZAMBOANGA SIBUGAY | On-Going | ₱14.9M |
| 25J00030 | May 23, 2025 | PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD), K1726+098.00 - K1726+253, K1726+253.00 - K1726+298.00, K1749+000.00 - K1749.635.00 | On-Going | ₱41.7M |
| 25J00065 | May 19, 2025 | ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO - PA-GADIAN - ZAMBOANGA CITY RD) | On-Going | ₱130.0M |
| 25J00028 | Apr 2, 2025 | CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SIBUGUEY RIVER, SIBUGUEY BR. SECTION (B00480MN) ALONG LANAO-PAGADIAN-ZAMBOANGA CITY RD (S01112MN) LEFT | On-Going | ₱96.2M |
| 25J00027 | Mar 14, 2025 | CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SIBUGUEY RIVER, PACKAGE 2, BARANGAY STA. BARBARA SECTION, IMELDA, ZAMBOANGA SIBUGAY | On-Going | ₱153.6M |
| 25J00029 | Mar 14, 2025 | CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SIBUGUEY RIVER, SIBUGUEY BR. SECTION (B00480MN) ALONG LANAO-PAGADIAN-ZAMBOANGA CITY RD (S01112MN) RIGHT | On-Going | ₱96.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.