Project 24JF0043
DPWH infrastructure contract
Contract ID:
24JF0043
Fingerprint:
e97b23480c3ba1…30fae50c7a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 15, 2024 (2 yrs 3 mo ago) · Target/actual end Jan 20, 2025
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH DRAINAGE AND LINE CANAL, BARANGAY CANACAN, KABASALAN, ZAMBOANGA SIBUGAY
Category:
Flood Control and Drainage
Implementing office:
DPWH Zamboanga Sibugay 2nd DEO · Region IX
Contractor:
DEBRIS ENTERPRISES AND CONSTRUCTION · DPWH contractor code 46713
Contract amount:
₱20,431,934.07 (₱20.4M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e2114782e581… | Jun 24, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA SIBUGAY | ₱20,431,934.07 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25J00032 | Jun 20, 2025 | ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO- PAGADIAN- ZAMBOANGA CITY RD) | On-Going | ₱112.1M |
| 25J00037 | May 30, 2025 | PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD), K1773+361.00 - K1775+181.00 | On-Going | ₱107.2M |
| 25J00138 | May 30, 2025 | ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO-PAGADIAN-ZAMBOANGA CITY RD) | On-Going | ₱42.8M |
| 25J00033 | Apr 2, 2025 | CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER, PHASE V, PACKAGE 3, BARANGAY F.L. PENA, KABASALAN, ZAMBOANGA SIBUGAY | On-Going | ₱141.6M |
| 25J00034 | Apr 2, 2025 | CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER, PHASE V, PACKAGE 4, BARANGAY F.L. PENA, KABASALAN, ZAMBOANGA SIBUGAY | On-Going | ₱141.5M |
| 25J00035 | Apr 2, 2025 | CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER, PHASE V, PACKAGE 2, BARANGAY F.L. PENA, KABASALAN, ZAMBOANGA SIBUGAY | On-Going | ₱140.7M |
| 25JF0026 | Mar 26, 2025 | CONSTRUCTION OF BOX CULVERT, BARANGAY TIGBANGAGAN, KABASALAN, ZAMBOANGA SIBUGAY | Completed | ₱3.2M |
| 25JF0040 | Feb 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING), BARANGAY PEÑARANDA, KABASALAN, ZAMBOANGA SIBUGAY | Completed | ₱3.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.