Project 24JJ0001
DPWH infrastructure contract
Contract ID:
24JJ0001
Fingerprint:
ae1f9ac3d6b60c…470bbcb1d1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2024 (2 yrs 8 mo ago) · Target/actual end Nov 14, 2024
Description:
PAVING OF UNPAVED ROADS -SECONDARY ROADS, LILOY-SIOCON RD-K2042+ 571 - K2044 + 500
Category:
Roads
Implementing office:
DPWH Zamboanga del Norte 4th DEO · Region IX
Contractor:
MJMARI BUILDERS AND DEVELOPMENT CORPORATION · DPWH contractor code 36434
As listed: MJMARI BUILDERS AND DEVELOPMENT CORPORATION (FORMERLY: MJMARI BUILDERS AND ENTERPRISES)
Contract amount:
₱53,344,235.00 (₱53.3M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 82154438697e… | Jan 30, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA DEL NORT | ₱51,743,907.95 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JJ0047 | Apr 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) AT (1) KAUSWAGAN ELEMENTARY SCHOOL, BALIGUIAN, ZN (2) BALIGUIAN CENTRAL SCHOOL, BALIGUIAN, ZN (3) S. CABRAL ELEMENTARY SCHOOL, SIOCON, ZN (4) SIBUCO CENTRAL SCHOOL, SIBUCO, ZN (5) SIRAWAI CENTRAL SCHOOL, | On-Going | ₱2.6M |
| 25JJ0004 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2064 + 728 - K2064 + 757, K2064 + 939 - K2064 + 972 | Completed | ₱13.4M |
| 25JJ0008 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2056 + 892 - K2056 + 942 | Completed | ₱24.7M |
| 25JJ0009 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2028 + 110 - K2028 + 124, K2029 + 560 - K2029 + 620, K2030 + 013 - K2030 + 043, K2030 + 452 - K2030 + 494, K2030 + 527 - K2030 + 552 | Completed | ₱38.0M |
| 25JJ0010 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 208 - K2031 + 235, K2031 + 847 - K2031 + 882 | Completed | ₱16.4M |
| 25JJ0016 | Mar 27, 2025 | PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2049 + 500 - K2051 + 800 | Completed | ₱76.7M |
| 25JJ0018 | Mar 27, 2025 | PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2040 + 250 - K2040 + 896 | On-Going | ₱21.9M |
| 25JJ0019 | Mar 27, 2025 | PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2053 + 600 - K2054 + 300 | On-Going | ₱24.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.