Project 24K00075
DPWH infrastructure contract
Contract ID:
24K00075
Fingerprint:
149dded92dd03b…d96a9015bd Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Aug 23, 2024 (2 yrs 2 mo ago)
Description:
CONST. OF BY-PASS AND DIVERSION ROADS, JCT. MARAMAG-MARADUGAO ROAD-JCT. LAMPANUSAN ROAD, PACKAGE 12, BUKIDNON
Category:
Roads
Implementing office:
DPWH Region X · Region X
Contractor:
C'ZARLES CONSTRUCTION & SUPPLY · DPWH contractor code 23426
Contract amount:
₱161,550,271.20 (₱161.6M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| eb8efe8a7fa3… | Aug 8, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION X | ₱161,550,271.20 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25K00229 | May 26, 2025 | CONSTRUCTION OF ROAD, FROM THE NATIONAL HIGHWAY TO LUMAGWAS-KIDANGGIN ROAD LEADING TO HOT SPRINGS, PANGANTUCAN, BUKIDNON | On-Going | ₱95.5M |
| 25KN0057 | May 23, 2025 | CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM (RWCS) IN PUBLIC FACILITIES: | Completed | ₱2.5M |
| 25K00312 | Apr 7, 2025 | CONSTRUCTION OF JCT. CAMP KIBARITAN-PANGANTUCAN - JCT GUINOYURAN-VALENCIA ROAD, PANGANTUCAN SECTION, PACKAGE 5, BUKIDNON | On-Going | ₱189.1M |
| 25K00267 | Apr 4, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARAMAG-MARADUGAO RD (UPSTREAM AND DOWNSTREAM) OF MULETA BRIDGE, PACKAGE 3, PANGANTUCAN, BUKIDNON | On-Going | ₱94.5M |
| 25K00268 | Apr 4, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARAMAG-MARADUGAO RD (UPSTREAM AND DOWNSTREAM) OF MULETA BRIDGE, PACKAGE 4, PANGANTUCAN, BUKIDNON | On-Going | ₱94.5M |
| 25K00269 | Apr 4, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGAYARAN RIVER (UPSTREAM) OF NABALIWA BRIDGE, PACKAGE 4, PANGANTUCAN, BUKIDNON | On-Going | ₱94.5M |
| 25K00270 | Apr 4, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGAYARAN RIVER (UPSTREAM) OF NABALIWA BRIDGE, PACKAGE 5, PANGANTUCAN, BUKIDNON | On-Going | ₱94.5M |
| 25KN0015 | Mar 26, 2025 | REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS, MARAMAG - MARADUGAO RD - K1588 + 054 - K1588 + 157 | Completed | ₱2.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.