Project 24K00475

DPWH infrastructure contract
Contract ID:
24K00475
Fingerprint:
54e400f9f5d9a1…828017efe4 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Oct 11, 2024 (2 yrs 1 mo ago)
Description:
CONSTRUCTION OF THREE-STOREY ENGINEERING BUILDING, PHASE III-CAMIGUIN POLYTECHNIC STATE COLLEGE
Category:
GAA 2024 SUCs Infrastructure Projects
Implementing office:
DPWH Region X · Region X
Contractor:
L&L CONSTRUCTION · DPWH contractor code 15108
As listed: L & L CONSTRUCTION
Contract amount:
₱19,860,007.03 (₱19.9M)
Funding source:
Outside Infra - GAA 2024 SUCs Infrastructure Projects
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26KE0004Jul 30, 2026REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS - CAMIGUIN CIRCUMFERENTIAL ROAD - K0005 + 934 - K0006 + 034On-Going₱8.7M
25KE0061Feb 10, 2026REPAIR/REHABILITATION OF 2 CLASSROOMS, BINUNSARAN ELEMENTARY SCHOOL, MAMBAJAO, CAMIGUINOn-Going₱1.3M
25KE0065Feb 10, 2026RESTORATION AND CONSERVATION OF GABALDON AND OTHER HERITAGE SCHOOL BUILDING, KUGUITA INTEGRATED SCHOOL, MAMBAJAO, CAMIGUINOn-Going₱4.5M
25KE0060Nov 6, 2025CONSTRUCTION OF SCHOOL BUILDING, MAGTING ELEMENTARY SCHOOL, MAGTING, MAMBAJAO, CAMIGUINOn-Going₱12.7M
25KE0038Sep 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT, BOARDWALK AND LANDSCAPING BARANGAY POBLACION, MAMBAJAO, CAMIGUINOn-Going₱49.2M
25KE0039Sep 29, 2025CONSTRUCTION OF BOARDWALK WITH VIEW DECK (OLD WHARF), PHASE II, MUNICIPAL PLAZA, BARANGAY POBLACION, MAMBAJAO, CAMIGUINOn-Going₱49.2M
25KE0017Jun 12, 2025CONSTRUCTION OF ROADS, BARANGAYS AGOHO, BUG-ONG AND MAGTING, MAMBAJAO, CAMIGUINOn-Going₱9.6M
25KE0041Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) SITIO BINUNSARAN, MAMBAJAO, CAMIGUINOn-Going₱9.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.