Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24K00519

DPWH infrastructure contract
Contract ID:
24K00519
Fingerprint:
776fc4002ac9fb…85188bba00 Verified
Status:
On-Going
Physical progress:
80.0%
Timeline:
Start Jan 7, 2025 (1 yr 10 mo ago)
Description:
ACCESS ROAD LEADING TO BUKIDNON AIRPORT (JCT. KKK ROAD/LANGCATAON PANGANTUCAN-JCT DON CARLOS-KADINGILAN ROAD/SAN NICOLAS (LANGCATAON, PANGANTUCAN-KAWILIHAN-MAHAYAHAY-PUALAS, DON CARLOS SECTION), PACKAGE 9, BUKIDNON
Category:
Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Implementing office:
DPWH Region X · Region X
Contractor:
ULTICON BUILDERS, INC. · DPWH contractor code 17267
Contract amount:
₱190,627,777.88 (₱190.6M)
Funding source:
Outside Infra - Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fbd4b6281bd4…Dec 27, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION X₱190,627,777.88

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25K00229May 26, 2025CONSTRUCTION OF ROAD, FROM THE NATIONAL HIGHWAY TO LUMAGWAS-KIDANGGIN ROAD LEADING TO HOT SPRINGS, PANGANTUCAN, BUKIDNONOn-Going₱95.5M
25KN0057May 23, 2025CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM (RWCS) IN PUBLIC FACILITIES:Completed₱2.5M
25K00312Apr 7, 2025CONSTRUCTION OF JCT. CAMP KIBARITAN-PANGANTUCAN - JCT GUINOYURAN-VALENCIA ROAD, PANGANTUCAN SECTION, PACKAGE 5, BUKIDNONOn-Going₱189.1M
25K00267Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARAMAG-MARADUGAO RD (UPSTREAM AND DOWNSTREAM) OF MULETA BRIDGE, PACKAGE 3, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00268Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARAMAG-MARADUGAO RD (UPSTREAM AND DOWNSTREAM) OF MULETA BRIDGE, PACKAGE 4, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00269Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGAYARAN RIVER (UPSTREAM) OF NABALIWA BRIDGE, PACKAGE 4, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00270Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGAYARAN RIVER (UPSTREAM) OF NABALIWA BRIDGE, PACKAGE 5, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25KN0015Mar 26, 2025REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS, MARAMAG - MARADUGAO RD - K1588 + 054 - K1588 + 157Completed₱2.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.