Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24LA0024

DPWH infrastructure contract
Contract ID:
24LA0024
Fingerprint:
f054651fff8c21…52c8055a91 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 29, 2024 (2 yrs 9 mo ago) · Target/actual end Dec 9, 2024
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), BARANGAY POBLACION, MAWAB, DAVAO DE ORO
Category:
GAA 2024 SSP
Implementing office:
Contract amount:
₱49,496,791.66 (₱49.5M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25L00109Sep 12, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - MAHARLIKA HIGHWAY - K1439+290 - K1439+920, DAVAO DE OROOn-Going₱225.7M
25LA0057Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAWAB MUNICIPAL HALL (PHASE III), MAWAB, DAVAO DE OROCompleted₱44.5M
25LA0066Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, HEADQUARTERS, 10TH INFANTRY (AGILA) DIVISION, PHILIPPINE ARMY, CAMP GEN MANUEL T. YAN, BARANGAY TUBURAN, MAWAB, DAVAO DE OROCompleted₱4.9M
25LA0089Jul 24, 2025CONSTRUCTION OF ROAD, POBLACION, MAWAB TO DIZON AREA, MAWAB, DAVAO DE OROOn-Going₱34.2M
25LA0072May 23, 2025CONCRETING OF BRGY. MIPANGI FMR, BRGY. MIPANGI, NABUNTURAN, DAVAO DE OROOn-Going₱14.9M
25LA0045Feb 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), PHASE 2, BARANGAY POBLACION, MAWAB, DAVAO DE OROCompleted₱49.5M
24L00288Jan 13, 2025MILITARY HOSPITAL - AFP CAMP GENERAL MANUEL T. YAN SR, DAVAO DE ORO (COMPOSTELA VALLEY)On-Going₱9.9M
24LA0137Jan 6, 2025CONSTRUCTION OF REVETMENT FLOOD CONTROL GARINAN CREEK, POBLACION, MAWAB, DAVAO DE OROOn-Going₱48.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.