Project 24LD0069
DPWH infrastructure contract
Contract ID:
24LD0069
Fingerprint:
5eec8e014d6808…ef7acf2455 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 24, 2024 (2 yrs 6 mo ago) · Target/actual end Sep 17, 2024
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE (BRIDGE SECTION) AT BARANGAY NEW CLARIN-PULANG LUPA, BANSALAN, DAVAO DEL SUR
Category:
GAA 2024 SSP
Implementing office:
DPWH Davao del Sur DEO · Region XI
Contractor:
K AND C BUILDERS (47505) / RCDG CONSTRUCTION CORPORATION · DPWH contractor code 5063
Contract amount:
₱67,550,000.00 (₱67.5M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LD0194 | Sep 22, 2025 | PREVENTIVE MAINTENANCE OF ROAD;: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS-COTABATO SECTION)-K1580+625-K1581+434, K1582+118-K1582+670, DAVAO DEL SUR | Completed | ₱96.5M |
| 25LD0170 | Jul 22, 2025 | CONSTRUCTION OF ROAD, BRGY. SIBAYAN, MUNICIPALITY OF BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0169 | Jun 25, 2025 | CONSTRUCTION OF CONCRETE REVETMENT/DIKE AT BARANGAY RIZAL, BANSALAN, DAVAO DEL SUR | Completed | ₱99.0M |
| 25LD0186 | Jun 25, 2025 | CONSTRUCTION OF ROAD AT BARANGAY DOLO, BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 24LD0215 | May 28, 2025 | CONCRETING OF FMR LOCATED AT BARANGAY LINAWAN, BANSALAN, DAVAO DEL SUR | Completed | ₱9.9M |
| 25LD0105 | Mar 24, 2025 | CONSTRUCTION OF SK FEDERATION MPB, PROVINCIAL CAPITOL, MATTI, DIGOS CITY, DAVAO DEL SUR | On-Going | ₱4.8M |
| 25LD0106 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. DOLO, BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0123 | Mar 24, 2025 | CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. DARAPUAY, BANSALAN, DAVAO DEL SUR | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.