Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24LG0050

DPWH infrastructure contract
Contract ID:
24LG0050
Fingerprint:
91b94a864a9de8…a682a1bd22 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 26, 2024 (2 yrs 7 mo ago) · Target/actual end Jun 22, 2024
Description:
CONCRETING OF BRGY. MAYO FMR,BRGY. MAYO, MATI CITY, DAVAO ORIENTAL
Category:
Roads
Implementing office:
Contractor:
RAKKI CORPORATION · DPWH contractor code 43053
Contract amount:
₱14,275,353.84 (₱14.3M)
Funding source:
Outside Infra - GAA 2024 DA FMR
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
71d810651fa7…Mar 14, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO ORIENTAL 2ND₱14,275,353.84

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25LG0098Feb 20, 2026CONSTRUCTION OF DIVERSION ROAD, BARANGAY SUDLON, SAN ISIDRO-BARANGAY MAMALI, MATI CITY, DAVAO ORIENTALOn-Going₱96.0M
25LG0101Feb 12, 2026CONSTRUCTION OF ROAD , BARANGAY DON SALVADOR LOPEZ PROPER TO CANGUSAN ELEMENTARY SCHOOL, CITY OF MATI, DAVAO ORIENTALOn-Going₱94.6M
25LG0096Feb 10, 2026CONSTRUCTION OF ROAD, DON MARTIN MARUNDAN LEADING TO SITIO DALAGUIT, DON MARTIN MARUNDAN, CITY OF MATI, DAVAO ORIENTALOn-Going₱94.6M
25L00138Oct 3, 2025CONSTRUCTION OF ACCESS ROAD LEADING TO MATI FISH PORT, PHASE 4, MATI CITY, DAVAO ORIENTALOn-Going₱283.7M
25L00157Aug 28, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PRES. DIOSDADO P. MACAPAGAL HI-WAY - K1719+712 - K1721+400, DAVAO ORIENTALOn-Going₱93.7M
25L00089Aug 20, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PRES. DIOSDADO P. MACAPAGAL NAT; HI-WAY - K1727+340-K1727+480, DAVAO ORIENTALOn-Going₱56.7M
25LG0081Jul 7, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- PRES. DIOSDADO P. MACAPAGAL NATL HI-WAY- K1731 + 000 - K1739 +000On-Going₱95.5M
25LG0092Jun 26, 2025CONSTRUCTION OF SCHOOL BUILDING, BASO ELEMENTARY SCHOOL, BARANGAY BADAS, CITY OF MATI, DAVAO ORIENTALOn-Going₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.