Project 24M00105
DPWH infrastructure contract
Contract ID:
24M00105
Fingerprint:
587a45680e53f7…4b809cf729 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 11, 2024 (2 yrs 7 mo ago) · Target/actual end Apr 20, 2025
Description:
ROAD WIDENING - DIGOS-MAKAR RD - K1613 + 996 - K1618 + 394, MALUNGON, SARANGANI
Category:
Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP, Traffic Engineering and Management System (including Road Safety Devices)
Implementing office:
DPWH Region XII · Region XII
Contractor:
AAA ROCK CONSTRUCTION CORPORATION (FORMERLY: DAVAO ROCK MIXER ENTERPRISES) (19250) / CHARIFER BUILDERS, INC. · DPWH contractor code 33498
Contract amount:
₱144,749,518.67 (₱144.7M)
Funding source:
Regular Infra - Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP, Traffic Engineering and Management System (including Road Safety Devices)
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ME0120 | Sep 19, 2025 | COMPLETION OF SITIO DATAL BACA MULTI-PURPOSE BUILDING, DATAL BATONG, MALUNGON, SARANGANI PROVINCE | Completed | ₱4.9M |
| 25ME0107 | Aug 15, 2025 | CONSTRUCTION (COMPLETION) TAMBAN SOLAR WATER SYSTEM, MALUNGON, SARANGANI PROVINCE | Completed | ₱3.0M |
| 25M00010 | Aug 14, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) -K1621+450 - K1621+459, MALUNGON, SARANGANI | On-Going | ₱8.0M |
| 25M00009 | Aug 6, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) -K1603+200 - K1603+229, MALUNGON, SARANGANI | On-Going | ₱30.0M |
| 25LE0039 | Jul 17, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DATU INTAN, STA. MARIA, DAVAO OCCIDENTAL | On-Going | ₱4.9M |
| 25ME0079 | Jul 15, 2025 | REHABILITATION OF MALUNGON MUNICIPAL GYMNASIUM, POBLACION, MALUNGON, SARANGANI PROVINCE | On-Going | ₱40.6M |
| 25M00013 | Jul 4, 2025 | ROAD WIDENING - MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) - K1612+961 - K1613+532, K1613+590 - K1613+996, K1620+098 - K1620+322 MALUNGON, SARANGANI | On-Going | ₱47.3M |
| 25ME0061 | May 30, 2025 | CONSTRUCTION OF BUAYAN RIS, PROPOSED 800M PROTECTION WORKS AT DOWNSTREAM AND UPSTREAM OF NIA DIVERSION WORKS (300M BOTH SIDES D/S AND 200M BOTH SIDES U/S, MALUNGON, SARANGANI PROVINCE | Completed | ₱14.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.