Project 24MB0067
DPWH infrastructure contract
Contract ID:
24MB0067
Fingerprint:
18482e1a66c44a…dbb8424867 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 2, 2024 (2 yrs 1 mo ago) · Target/actual end Jan 14, 2025
Description:
CONCRETING OF BARANGAY POBLACION TO DOLE AGRI AREA BARANGAY CANNERY ROAD, POLOMOLOK, SOUTH COTABATO
Category:
GAA 2024 SSP
Implementing office:
DPWH South Cotabato 1st DEO · Region XII
Contractor:
CONCRETE WORKS CONSTRUCTION, INC. (FORMERLY: UNIFIED WORKERS CONSTRUCTION & DEVELOPMENT MPC, INC.) · DPWH contractor code 36530
Contract amount:
₱9,853,917.39 (₱9.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MB0145 | May 11, 2026 | CONSTRUCTION OF SCHOOL HEALTH FACILITIES, POBLACION POLOMOLOK NATIONAL HIGH SCHOOL, POLOMOLOK, SOUTH COTABATO | On-Going | ₱2.9M |
| 25MB0123 | Nov 10, 2025 | CONCRETING OF SITIO PALACASAM TO SITIO ALNAMANG, BRGY. PALKAN FMR, BRGY. PALKAN, POLOMOLOK, SOUTH COTABATO | Completed | ₱12.2M |
| 25MB0111 | Oct 6, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT UPPER KLINAN ELEMENTARY SCHOOL, BARANGAY UPPER KLINAN, POLOMOLOK, SOUTH COTABATO | On-Going | ₱4.9M |
| 25MB0109 | Sep 22, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY CANNERY SITE, POLOMOLOK, SOUTH COTABATO | Completed | ₱4.8M |
| 25MB0133 | Aug 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, LAMCALIAF INTEGRATED SCHOOL, BRGY. LAMCALIAF, POLOMOLOK, SOUTH COTABATO | Completed | ₱5.0M |
| 25MB0135 | Aug 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, PALKAN ELEMENTARY SCHOOL, BRGY. PALKAN, POLOMOLOK, SOUTH COTABATO | Completed | ₱4.9M |
| 24M00221 | Jul 23, 2025 | CONSTRUCTION OF BRIDGE ALONG MARBEL-MAKAR ROAD, K1670 + 075, POLOMOLOK, SOUTH COTABATO | Completed | ₱28.7M |
| 25MB0044 | Jul 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), POLOMOLOK CREEK INTEGRATED SCHOOL, BARANGAY MAGSAYSAY, POLOMOLOK, SOUTH COTABATO | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.