Project 24MD0018
DPWH infrastructure contract
Contract ID:
24MD0018
Fingerprint:
1e4f12716c7bf0…0a1d860248 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 19, 2024 (2 yrs 8 mo ago) · Target/actual end Dec 18, 2024
Description:
JCT. DAVAO-COTABATO (CROSSING BAGUER)-SITIO DALUMANGKOM-SITIO LAMPAKI ROAD, ALAMADA, NORTH COTABATO, PACKAGE I, ALAMADA, COTABATO
Category:
Roads
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contractor:
LLABAN CONSTRUCTION & SUPPLY (FORMERLY: LLABAN CON · DPWH contractor code 29504
Contract amount:
₱95,534,999.99 (₱95.5M)
Funding source:
Regular Infra - GAA 2024 CP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MD0044 | Jul 28, 2025 | CONSTRUCTION OF ROAD, SITIO PINAMULAAN - BARANGAY NORTH MANUANGAN - BARANGAY SOUTH MANUANGAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0059 | Jul 7, 2025 | JCT. DAVAO - COTABATO (CROSSING BAGUER) - SITIO DALUMANGKOM - SITIO LAMPAKI ROAD, PIGKAWAYAN, NORTH COTABATO | Completed | ₱65.5M |
| 25MD0012 | Mar 6, 2025 | CONSTRUCTION OF ROAD JCT. HIGHWAY - BULUAN ROAD, BARANGAY BULUAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0030 | Mar 6, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY CAPAYURAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0031 | Feb 27, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALOGO RIVER, UPSTREAM OF BALOGO BRIDGE, BARANGAY BALOGO, PIGCAWAYAN, COTABATO | Completed | ₱94.7M |
| 25MD0038 | Feb 27, 2025 | CONSTRUCTION OF BALOGO RIVER FLOOD CONTROL STRUCTURE, ANICK SECTION, BARANGAY ANICK, PIGCAWAYAN, COTABATO | Completed | ₱94.4M |
| 24MD0066 | May 15, 2024 | CONCRETING OF BRGY. MALU-AU TO BRGY. NEW CULASI FMR, BRGY. MALU-AU AND BRGY. NEW CULASI, PIGCAWAYAN, COTABATO | Completed | ₱9.9M |
| 24MD0075 | May 15, 2024 | CONCRETING OF BRGY. BALOGO TO SITIO PAGLAUM FMR, BRGY. BALOGO, PIGCAWAYAN, COTABATO | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.