Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24MD0089

DPWH infrastructure contract
Contract ID:
24MD0089
Fingerprint:
2c880568ae1710…356c1ee05d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 7, 2025 (1 yr 8 mo ago) · Target/actual end Mar 2, 2026
Description:
CONCRETING OF JUNCTION PROVINCIAL ROAD AT BARANGAY SILIK TO PAIDU PULANGI, PIKIT, NORTH COTABATO
Category:
PAMANA 2024
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contractor:
H-ROYAL CONSTRUCTION · DPWH contractor code 40051
Contract amount:
₱91,395,119.37 (₱91.4M)
Funding source:
Outside Infra - PAMANA 2024
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MD0080Apr 7, 2026CONSTRUCTION OF 1STY 3CL SCHOOL BUIDING LANGAYEN ES, PIKIT, NORTH COTABATOOn-Going₱9.5M
22MD0074Apr 5, 2022CONSTRUCTION OF BRIDGE - CONSTRUCTION OF BRIDGE IN SILIK, PIKIT, NORTH COTABATOCompleted₱29.2M
22MD0015Feb 2, 2022CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY KOLAMBOG, PIKIT, NORTH COTABATOCompleted₱4.9M
22MD0016Feb 2, 2022CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY PAIDU PULANGI, PIKIT, NORTH COTABATOCompleted₱4.9M
22MD0017Feb 2, 2022CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY PUNOL, PIKIT, NORTH COTABATOCompleted₱4.9M
21MD0023Apr 7, 2021CONCRETING OF G. GOKOTANO STREET, BARANGAY POBLACION, PIKIT, NORTH COTABATOCompleted₱2.0M
20MD0005Nov 25, 2020PREVENTIVE MAINTENANCE OF ROADS: ASPHALT OVERLAY ALONG DUALING-BALIKI-SILIK ROAD (S00810MN), ALEOSAN AND PIKIT, NORTH COTABATOCompleted₱42.2M
19MD0102Dec 6, 2019CONCRETING OF BOUNDARY BRGY. POBLACION - GLI-GLI (SITIO MANDING), BRGY. POBLACION FMR, BRGY. POBLACION, PIKIT, NORTH COTABATOCompleted₱9.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.