Project 24MH0112
DPWH infrastructure contract
Contract ID:
24MH0112
Fingerprint:
d06f98b0ce4158…240f2f4e3e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 5, 2024 (2 yrs 5 mo ago) · Target/actual end Dec 10, 2024
Description:
CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM
Category:
Water Provision and Storage
Implementing office:
DPWH Sultan Kudarat 2nd DEO · Region XII
Contractor:
ALBANOR CONSTRUCTION · DPWH contractor code 41645
Contract amount:
₱2,893,016.36 (₱2.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 336bd9873380… | May 29, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SULTAN KUDARAT 2ND | ₱2,893,016.36 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MH0124 | Aug 19, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM | Completed | ₱2.6M |
| 25MH0022 | Mar 25, 2025 | CONSTRUCTION OF RIVER BANK PROTECTION (UPSTREAM LEFT SIDE), BARANGAY BARONGIS, PALIMBANG, SULTAN KUDARAT | Completed | ₱120.6M |
| 25MH0090 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BALIANGO ELEMENTARY SCHOOL, BARANGAY BALIANGO, PALIMBANG, SULTAN KUDARAT | Completed | ₱3.8M |
| 25MH0092 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY KOLONGKOLONG, PALIMBANG, SULTAN KUDARAT | Completed | ₱2.9M |
| 25MH0094 | Mar 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, PALIMBANG, SULTAN KUDARAT | Completed | ₱4.8M |
| 25MH0003 | Mar 19, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K1998+000 - K1999+197 | Completed | ₱21.0M |
| 25MH0004 | Mar 19, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K2006+000 - K2006+892 | Completed | ₱15.7M |
| 25MH0005 | Mar 17, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K2029+246 - K2030+000, K2044+087 - K2044+387 | Completed | ₱18.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.